Many projects in Thyborøn
The silo project is moving forward according to
plan
Production Manager Lars Skøtt Nielsen states that the schedule
with regard to the establishing of six new raw product silos at the
factory in Thyborøn is being followed.
As mentioned in the last edition of 999 News, the first two silos
have already been put into use, and all six silos have now been
erected and covered with exterior plates.
All six silos will be ready in time for the sand eel season.

A pumping system is ready
The new pumping system, which is to transport the raw product from
the piers to the silos, is also progressing according to
plan.
The pumping system from pier 2 will be ready in time for the sand
eel season while the Redler system from pier 1 will not be replaced
with a pumping system until after the sand eel season.
Evaporator 3 will also be ready
Evaporator 3 will also be operation ready before the sand eel
season.
A condenser is expected back in late February from a warranty
repair and will be tested in February and March.
Faster unloading
Another pump to the transportation system has been established
from build-up to production.
This will mean that unloading the raw products from the trucks can
be done faster than before.
Calm period utilized for maintenance
In December and early January, the high activity level experienced
in November has been replaced by a very calm period in the
production with moderate supplies of raw products due to the amount
of wind in this period.
- Otherwise, the annual maintenance of the entire production
machinery is taking place according to plan, Lars Skøtt Nielsen
closes.
- TripleNine wants to create its own raw material pool8. december 2011Read More
- The current limits must be exceeded6. februar 2012Read More
- Promega-3 - New product line for pet food8. december 2011Read More
- How do we secure the value and growth of TripleNine?6. februar 2012Read More
- TripleNine shows a profit of 49 million Kroner8. december 2011Read More